New Dates for our Expansion buildingworks


We are excited that things are now starting to happen again, and you will start to see more happening. As you know, dates are subject to change and I will keep you updated if there are any changes.

DateWhat is happening?
21st NovTemporary Kitchen installed on site
Part of the lower playground fenced off to get ready
for larger site works
21st-24th NovSite preparation works by Morgan Sindell site team.
25th NovContainer storage installed on site.
Train and boat removed. (They will be returned when buildingworks are completed)
From 5th DecAll families enter through Springfield Park Hill Road to the school field.
All other entrance gates for children and families are closed.
Lunch eaten in the lower hall.
Site fencing installed in lower playground and lunchbar.
From 14th DecDemolition of the lunchbar starts